Construction - Move In Tasks Phase

Name
Begin date
End date
Resources
*Perform pressure test #2 for gound loop tubing
2/9:    4:20pm: 40psi.  4:40pm: 40psi.
2/10:  5:00pm: 34psi (dropped 6psi in 24 hours).
           5:35pm: 51psi,  5:55pm: 51psi.
2/11:  9:30am: 42psi (dropped 9psi in 16 hours, 18%).
2/13:  11:45am: 27psi  (dropped 24psi in 66 hours, 47%)
2/11/13
2/12/13
Plumbing - install all underslab septic lines, supply lines and fittings
11/27/12
12/19/12
County Inspection: 3150 Underslab Plumbing
12/19/12
12/20/12
*Heating HVAC ductwork: final design and order
12/17/12
1/5/13
*Heating HVAC ductwork: deliver to site
1/7/13
2/1/13
Plumbing: reposition PEX line in way of 8" HVAC tube
2/7/13
2/8/13
*Purchase HVAC Insulation
2/4/13
2/5/13
*Purchase HVAC Glue
Per Pat Middleton: All purpose heavy bodied PVC cement
 - multi purpose for white & black connections, regular primer.
Meschers: Terry: 541-548-6400 - order has arrived: IPS Weld-On 719
Quantity: 48 quarts / 4 cases of 12 quarts each
2/5/13
2/20/13
Purchase HVAC Sheet Metal Tapping Screws
Size TBD.
3/8/13
3/9/13
Purchase HVAC Primer
Per Pat Middleton: regular primer.
3/12/13
3/13/13
Purchase HVAC spray insulation for going through cement trenches
Already have some cans, are these good enough?
2/1/13
2/2/13
ICF Delivery to site
2/1/13
2/15/13
All Architectural plan updates
2/11/13
3/5/13
*Final Heating and Plumbing Plan updates
2/25/13
3/8/13
Cement cuts for all footing trenches and ICF overlap
3/7/13
3/13/13
Pressure test all register boot boxes
3/26/13
3/27/13
*Install HVAC tubes and fittings
  Scope of work:
  a) Finish trenching lines for 6", 8" and 10" duct work.
     Level trenches and install bedding material.
     Finalize supply and return connection locations for proposed
     heat pump location.
     Determine final connection fabrications and runs to reach 144 square inches
    for both supply and return lines.
  b) Assist in installing duct work per manufacturers' recommendations
     ensuring level lines and register boots, and ensuring proper depth
     below slab height and proper bedding and support for all tubes and
     fittings.
     Duct tubes and fittings are already on site.
     Insulation for tubes is already on site.
     Glue will be on site.
     . Per EST: 2x 8"x8' strips of insulation board are laid down in the
       trenches to form a "V" for insulating the ducts.
  c) Perform pressure test as long as it is cost effective.
  d) Follow on:
     1) Assist in installing heat pump:
        . Supply connections for the heat pump supply (downflow) and return
          (side) to the under-slab duct work.
        . Specify, possibly supply, platform for the heat pump to sit on
          and have connections underneath.
        . Assist as determined in connecting the heat pump to duct work, flow
          control center and thermostatic controls.
     2) Test and qualify final installation.  Supply supporting paperwork for
        Oregon tax credit (ground source heat pump).
3/13/13
3/27/13
Build stem walls: entrance & BR2
3/28/13
3/30/13
Purchase and deliver ICF rebar
4/1/13
4/2/13
Install ICF pony and full exterior module wall forms only
4/1/13
4/6/13
Install all ICF plumbing components
4/2/13
4/3/13
Jesse: final plumbing inspection/bathtub access prior to pour
4/2/13
4/3/13
*Install all under-slab electrical components
4/1/13
4/5/13
*Install all ICF electrical components
4/2/13
4/12/13
Install ICF rebar
4/8/13
4/12/13
Install ICF cement
4/10/13
4/12/13
Install front door grating block outs
4/11/13
4/12/13
County inspection: 1400 Perimeter Slab Insulation
4/3/13
4/4/13
County inspection: 2300 Underslab Mechanical
4/3/13
4/4/13
County inspection: 4150 Underslab Electric
4/9/13
4/10/13
Purchase and deliver 6-mil vapor barrier
4/9/13
4/10/13
Install 6-mil vapor barrier
4/10/13
4/11/13
Prepare footings and module walls for slab pour (sand and expansion joints)
Level gravel, compact (1 day)
Floating slab:
 1 - Layer of sand on top of all footings
 2 - Expansion joints all along internal module walls
All other misc prep work
4/8/13
4/11/13
County inspection: 1420 Insulation Vapor Retarder
4/10/13
4/11/13
Pour both module slabs
Includes pouring the front door grate area floor
Pour/finish main slab -1 day
Pour/finish studio slab - 1 day
Slabs cure - 2 days (weekend)
4/12/13
4/13/13
Purchase and deliver front door grating material
4/8/13
4/9/13
Install front door grate plug
5/3/13
5/4/13
*Order and deliver shower/tub
3/18/13
4/24/13
*Order and receive vault wall building & rebar materials
02/15/2013   8” block ST     16” block TT       16” block ST
Totals                  129                     369                       143
3 weeks order to delivery
3/18/13
4/18/13
Install interior wall, door and ceiling framing
Dry Stack wall construction (outside walls only: 2): - 2 days
Interior wall framing - 3 days
Interior ceiling framing - 1 day
4/16/13
5/18/13
Electrical: Install main and sub electrical panels in utility room
4/22/13
4/23/13
County inspection: 4225 Service or Feeder
4/24/13
4/25/13
PPL: Switch from temp to permanent power
4/25/13
5/7/13
County inspection: 4220 Electrical Service
5/24/13
5/25/13
*Purchase and deliver vault door
4/8/13
5/15/13
County inspection: 1260 Framing
5/24/13
5/25/13
*Install vault door - Preliminary
Hang door, rough align.
6/10/13
7/9/13
Finalize bids on exterior windows and airlock doors
4/16/13
4/17/13
*Review and select bid
4/17/13
4/20/13
*Purchase and deliver windows and airlock doors
4/25/13
5/23/13
Install exterior window walls and airlock door windows
Set exterior windows/doors (when on site) - 2 days
5/22/13
5/23/13
*Electrical: Rough: Install outlets, data, switches to all drywall locations
Rough interior electrical - 5 days
Me - 15 days
All drywall outlets, switches,data,wall&O/H lights.
5/6/13
5/30/13
*Electrical: Rough: Install outlets, data, switches to all critical locations
Rough interior electrical - 2 days
Me - 6 days
Kitchen conduit pull, lights and outlets; refrigerator; septic conduit pull; utility room/bathroom outlets and hookups; server room outlets, MBR lights and outlets.
5/30/13
7/13/13
County inspection: 4500 Rough Electrical
5/24/13
5/25/13
Plumbing: Install rough plumbing
Venting, tub/shower trap and placement, water line rough in, valves rough in, vents run.  Pressure test.
5/3/13
5/22/13
County inspection: 3502 Top Out Rough Plumbing
5/24/13
5/25/13
Install Interior Wall Insulation
5/31/13
6/1/13
Drywall all rooms and ceilings
6/3/13
6/13/13
*Paint all drywall walls and ceilings
6/13/13
6/18/13
*Purchase and deliver cabinets.
millwork,cabinets,cabinet hardware
5/2/13
6/20/13
Install kitchen cabinets
Install cabinets/sub-tops - 2 days

6/20/13
6/26/13
*Purchase and deliver kitchen stove, stovetop, dishwasher and range hood
Also need countertops and light fixture (fan)
5/17/13
6/20/13
Install kitchen stove, stovetop and range fan/light
6/25/13
7/19/13
*Purchase and deliver toilets, sinks, heater, fixtures
5/13/13
10/5/13
Plumbing: Install remaining plumbing items
Hot water heater,  shower/tub fittings, toilets, sinks, fixtures, etc.
6/24/13
10/5/13
HVAC: Contact and have available HVAC independent contractor
3/4/13
3/16/13
*HVAC: above slab ducts, registers and venting
Install ducting and registers as required.
Requires cement cut south of hallway rough door opening to provide duct and electrical passthrough to the side of the hallway door.
Possible use of left over PVC 6" and 8" ducts.
 . BR2 and Dining area registers to point towards exterior windows to keep them clear
Install all vents to outside: bathrooms, dryer, kitchen
5/20/13
5/24/13
HVAC: Purchase and deliver thermostat
5/2/13
5/11/13
*Purchase Heat Pump and have it delivered to site
3 weeks order to delivery
4/17/13
5/22/13
HVAC: Install remainder of above slab items, connect to Heat Pump
Install above slab HVAC ducts, etc.
5/20/13
5/23/13
*HVAC: Install Heat Pump
5/20/13
5/21/13
HVAC: Heat Pump Tested and Operational
5/28/13
5/29/13
County Inspection: 4550 Limited Energy
5/24/13
5/25/13
*Purchase and deliver first set of internal doors
Seven doors: Garage entry, common wall door, three bathroom doors, master bedroom, server room.
Doors and hardware.
5/2/13
6/15/13
Install first set of internal doors - Prelimimary
Hang doors only.
6/25/13
7/3/13
*Get trencher back on site
4/17/13
4/18/13
*Trench remaining data line to power pole and install conduit
4/17/13
4/19/13
*Electrical: Install data and telephone lines to master bedroom
Install wiring.
6/21/13
6/22/13
Purchase, deliver and install computer rack hardware
5/28/13
6/21/13
*Get telephone/ISP setup and connected
5/28/13
6/5/13
*Move bulk of items (garage, etc.) from rental to site
6/17/13
6/18/13
*Move remaining items from rental to site
Includes moving, cleaning and hooking up refrigerator, washer and dryer.
6/25/13
6/26/13
*Clean and return rental house
6/26/13
7/2/13