Construction - Initial Phase
|
Name |
Begin date |
End date |
Resources |
Finalize Architectural Plans
|
2/16/12
|
5/16/12
| |
Finalize EST footing and structural plans
|
2/16/12
|
5/16/12
| |
Obtain Architectural Committee approval
|
3/19/12
|
3/27/12
| |
Obtain County permits
|
5/17/12
|
6/22/12
| |
Surveying
|
5/29/12
|
5/31/12
| |
Delay: not submitted
|
4/2/12
|
5/16/12
| |
Grade and install driveway
|
6/18/12
|
6/22/12
| |
Construction trailer registration and move to site
|
6/15/12
|
6/23/12
| |
Grade and install building pad
|
6/21/12
|
6/26/12
| |
Final preparation for soils inspection (taking out all soft spots)
|
8/20/12
|
8/28/12
| |
Obtain soils inspection report
|
8/27/12
|
8/28/12
| |
County inspection: 3300A Water Service
|
8/22/12
|
8/23/12
| |
Install temporary water
|
9/5/12
|
9/13/12
| |
County Inspection: 4000 Temporary Power Service
|
9/11/12
|
9/12/12
| |
Install temporary electrical
|
8/9/12
|
9/27/12
| |
Delay: schedule slip
|
6/22/12
|
9/11/12
| |
Electrical - install first module wall and roof items
|
9/14/12
|
9/18/12
| |
County Inspection: 1110A Footing
|
9/12/12
|
9/13/12
| |
County Inspection: 1130A Foundation Wall/Rebar
|
9/19/12
|
9/20/12
| |
EST - construct first module
|
9/11/12
|
9/21/12
| |
Electrical - install second module wall and roof items
|
9/25/12
|
9/28/12
| |
County Inspection: 1110B Footing
|
9/21/12
|
9/22/12
| |
County Inspection: 1130B Foundation Wall/Rebar
|
9/28/12
|
9/29/12
| |
EST - construct second module
|
9/21/12
|
10/2/12
| |
County Inspection: 1110C Footing
|
10/2/12
|
10/3/12
| |
County Inspection: 1190 Retaining Wall
|
10/2/12
|
10/3/12
| |
EST - construct garage walls
|
10/2/12
|
10/4/12
| |
County Inspection: 1110D Footing
|
10/4/12
|
10/5/12
| |
EST - construct window wall footing
|
10/5/12
|
10/10/12
| |
Delay: information unavailable
|
10/9/12
|
12/15/12
| |
Deliver exterior insulation
|
10/29/12
|
10/30/12
| |
EST - waterproof and insulate exterior
|
11/5/12
|
11/10/12
| |
HVAC - order and deliver ground loops
1 coil damaged first shipment received 10/2. Replacement coil received 10/11. |
9/24/12
|
10/12/12
| |
HVAC/Excavator - excavate and prepare ground loop field
|
10/25/12
|
10/30/12
| |
HVAC - install ground loops
|
10/30/12
|
10/31/12
| |
HVAC - pressure test ground loops
|
10/31/12
|
11/2/12
| |
County inspection: 2300A Rough Mechanical: ground loops
|
11/1/12
|
11/2/12
| |
HVAC - cover ground loops
|
11/5/12
|
11/6/12
| |
Excavator - install septic tank
|
10/1/12
|
10/6/12
| |
Excavator - install leech field and connecting lines
|
10/1/12
|
11/3/12
| |
Electrical - install septic tank controls and test
|
11/5/12
|
11/8/12
| |
County Inspection: 3201A Sewer Connection
|
11/1/12
|
11/2/12
| |
County inspection: 3201B Sewer Connection
|
11/8/12
|
11/9/12
| |
County Certificate: Septic
|
11/15/12
|
12/13/12
| |
Excavator - obtain and deliver all required dirt
|
10/23/12
|
11/27/12
| |
County Inspection: 4140 Underground Electric
|
11/1/12
|
11/2/12
| |
Excavator - cover structure
|
11/6/12
|
11/29/12
| |
Excavator - install perimeter drain
|
11/5/12
|
11/6/12
| |
Excavator - install earthtube
|
11/7/12
|
11/8/12
| |
Excavator - install drywells for perimeter drain
|
11/30/12
|
12/4/12
| |
County Inspection: 3300B Water Service
|
11/1/12
|
11/2/12
| |
Plumbing - install water line to house
|
11/2/12
|
11/3/12
| |
Electrical - install all below grade conduit connections to house
All conduit to service panel, to house, to battery house, and data (telephone). |
9/19/12
|
11/29/12
| |
Electrical - install service panel
|
11/16/12
|
11/17/12
|
Ganttproject (2.0.10) | ganttproject.biz
8/2/13 - 12:00:00 AM |