Construction - Final Inspections Phase
|
Name |
Begin date |
End date |
Resources |
*Electrical: Install trim required for final inspection.
|
6/21/13
|
7/30/13
| |
*Miscellaneous items required for house final
Door outside temporary landings. |
7/19/13
|
7/25/13
| |
*Install finish surfaces: Walls,Ceiling,Floor,Baseboard
|
7/31/13
|
8/1/13
| |
County inspection: 3130 Footing/Foundation Drains
|
7/31/13
|
8/1/13
| |
County inspection: 3131 SIte Drainage-Roof drain/foundation
|
7/31/13
|
8/1/13
| |
County inspection: 3411 Perimeter Rain Drains
|
7/31/13
|
8/1/13
| |
County inspection: 2100 HVAC/Heat Pump system
|
7/31/13
|
8/1/13
| |
County inspection: 2999 Final Mechanical
|
7/29/13
|
7/30/13
| |
County inspection: 3999 Final Plumbing
|
7/29/13
|
7/30/13
| |
County inspection: 4999 Final Electrical
|
7/29/13
|
7/30/13
| |
County inspection: 1990 Final Inspection - LDC (driveway)
|
7/30/13
|
7/31/13
| |
County inspection: 1999 Final Building
|
7/31/13
|
8/1/13
|