Construction - Completion Phase

Name
Begin date
End date
Resources
Apply/Get loan
8/1/13
10/23/17
Owner
Get Garage bid and official draft design documents
Finalize garage design details with Carlos
Get bid from Jeff
Get submittal quality design files from Jeff
EST or local general to have Oregon Contractor's license
6/30/14
10/30/17
Owner
Get concrete plaster finish bid
Get bid from Marc
6/3/14
7/28/14
Owner
Stain and finish cabinets and doors
8/9/13
8/30/13
Owner
Purchase and install cabinet hardware
8/28/13
8/29/13
Owner
Purchase and install water heater blanket and timer
8/21/13
9/6/13
Owner
Purchase and install kitchen undercabinet LED task lighting
12/4/13
8/22/14
Owner
Finish concrete walls and floors 80%
1/20/16
9/22/17
Owner, Hitson
Plaster 80% interior bare concrete
1/20/16
3/2/16
Hitson
Plaster Studio
1/20/16
1/28/16
Hitson
Plaster BR2
2/2/16
2/3/16
Hitson
Plaster Office
2/4/16
2/5/16
Hitson
Plaster BM half dome
2/8/16
2/9/16
Hitson
Plaster Kitchen
2/12/16
2/12/16
Hitson
Plaster LM 3/4 dome
2/16/16
2/19/16
Hitson
Plaster remaining 80%
2/24/16
3/2/16
Hitson
Paint 80% interior plaster
2/5/16
8/5/16
Owner
Paint Studio
5 days, over weekend
2/5/16
2/9/16
Owner
Paint BM Half Dome
4/25/16
5/3/16
Owner
Paint BR2 & South overhang/walls
4 days over weekend (and move items out)
5/4/16
5/10/16
Owner
Paint Kitchen & Front Door airlock
3 days over weekend
7/19/16
7/19/16
Owner
Paint LM Full Dome and walls
12 days over weekend
7/26/16
8/5/16
Owner
Floor Tile 80%
2/1/16
9/22/17
Owner
*Purchase and deliver Studio and Office Tile Materials
2/1/16
2/4/16
Owner
Tile Studio
2/10/16
4/29/16
Owner
*Purchase and deliver Tile materials for remaining LM areas
12/5/16
12/7/16
Owner
Tile BR2 with hallway entrance
23 days (approx 162 sf BR2, 24 sf hallway entrance)
3 days preparation (cleaning, edging, antiF, baselining)
18 days tiling
4 days grouting/edging
1 week Holiday break
Elapsed days: 42
12/12/16
1/20/17
Owner
Tile north LM partial
57 days (approx 408 sf / 203 pcs) (52+36+36+34/36+22/26+17)
10 days preparation (clearing, cleaning, edging, antiF, baselining)
35 days tiling
12 days grouting/edging
1/23/17
5/26/17
Owner
Tile Office
17 days (approx 112 sf, 54 pieces)
4 days preparation (clearing, vents, cleaning, edging, antiF, baselining)
9 days tiling
4 days grouting/edging
4/10/17
5/2/17
Owner
Tile Kitchen
14 days (approx 70 sf)
2 days preparation (clearing, cleaning, edging, antiF, baselining)
7 days tiling
5 days grouting/edging/re-setup
5/3/17
5/19/17
Owner
Tile south LM partial
38 days (approx 266 sf)
7 days preparation (clearing, vents/outlet, 2xsensorsruns, cleaning, edging, antiF, baselining)
23 days tiling
7/8 days grouting/edging
5/23/17
7/13/17
Owner
Tiling Finish Tasks
X MBR (1):
  X Touch up base paint
X Office/LM (2):
  X Finish covering/grouting 3 vents
Bathrooms/Utility (3):
  Finish grout edging
  Finish tub grout
  Finish Heat Pump sleaves and caps
LM Media Center/Dining (1):
  Install electrical floor outlets
7/13/17
9/22/17
Owner
Plaster, Painting, Tiling completed *MILESTONE*
9/25/17
9/25/17
Owner
Stucco all external house walls (base) *MILESTONE*
10/10/13
11/18/13
Owner
Laying/block down slab exterior 8" interim insulation
11/19/13
11/19/13
Owner
Finish concrete walls and floors 20%
5/9/16
12/9/16
Owner, Hitson
Prep utility, server, vault, 1/2 bath, MBR
5 days over weekend
1/2 bath
  Clean expansion joint
Remove server room and vault contents
  Cut outlet power
  Remove server case from wall
  Loosen all power and data conduits and boxes from wall
  Clean expansion joints
MBR
  Move bedroom items to BR2
  Clean expansion joints
  Wash all laundry
Utility room
  Remove contents
  Move washer/dryer
  Loosen all power conduits and piping from wall (accessable only)
  Clean expansion joints (accessable only)
5/9/16
5/13/16
Owner
Plumbing prep: Utility and Half Bath
Pull Half Bath toilet, hot water heater and heat pump tank
5/13/16
5/13/16
Jesse
Plaster 20% interior bare concrete Utility, Half-Bath first
Utility room
Half Bath
Vault (entirely cover door, hinges, flange)
Server room
MBR
5/13/16
6/1/16
Hitson
Plaster Utility and Half Bath
Utility room
Half Bath
Vault (entirely cover door, hinges, flange)
Server room
MBR
5/13/16
5/16/16
Hitson
Plaster Vault and Server Room
Utility room
Half Bath
Vault (entirely cover door, hinges, flange)
Server room
MBR
5/17/16
5/19/16
Hitson
Plaster MBR
Utility room
Half Bath
Vault (entirely cover door, hinges, flange)
Server room
MBR
5/27/16
6/1/16
Hitson
Finish Patch Areas Utility and Half Bath
5/17/16
5/27/16
Owner
Floor Prep: Utility and Half Bath
Day 1: Strip sealer
Day 2: Edging and Anti-fracture membrane. Rough tile layout.
Day 3: Thin-set leveling.  Layout exact tile placement.
5/17/16
5/19/16
Owner
Floor Tile patch: Utility and Half Bath
3 days over weekend
5/20/16
5/23/16
Owner
Floor Grout/edging patch: Utility and Half Bath
Grout near Utility room edge first
Install patch edging right after grouting drys enough to remove edging wood
5/24/16
5/25/16
Owner
Paint 20% Utility and Half Bath
All three coats in one day, forced drying with fan
 8am-10am, 12pm-2pm, 4pm-6pm
5/25/16
5/25/16
Owner
Floor cleanup patch: Utility and Half Bath
Wash, remove any grit, etc.  Remove all tape from lines, etc., reattach to wall, cleanup.
5/27/16
5/27/16
Owner
Plumbing work
Reinstall Half Bath toilet, hot water heater and heat pump tank
Pull Full Bath toilet
5/27/16
5/27/16
Jesse
*Purchase and deliver Tile materials for MBR, hall, baths, utility, server and vault
5/16/16
5/17/16
Owner
Floor Tile: Utility and baths remaining areas
Remaining Utility area.  All of the Full Bathroom
11 days over weekend
5/31/16
6/8/16
Owner
Plumbing finish
Reinstall Full Bath Toilet
6/7/16
6/7/16
Jesse
Start: Paint 20% Remaining
Vault, Server Room, MBR
1 day start
6/8/16
6/8/16
Owner
Downtime
6/9/16
6/15/16
Owner
Finish: Paint 20% Remaining
Vault, Server Room, MBR
7 days over weekend
6/16/16
6/24/16
Owner
Floor Tile 20%
Water Heater patching (wall,floor)
Day 1: Pull water heater, strip cement patch, sealer, self-leveler
Day 2: 8-9am: wall primer, 11-12pm: wall primer, 2-3pm: finish coat
           4-5pm: Tile
Day 3: Reinstall water heater

Priority:
  Utility-A,1/2 bath, Bath-A
    Marc/Jesse
  Utility-B, Bath-B
    Jesse
  MBR, Hallway
  Vault, ServerRoom
6/27/16
12/9/16
Owner
Tile Vault
9 days over weekend:
3 days prep (all): Clean, edging, antiF
   Vault level
4 days tiling
1 day grouting
1 day edging, cleanup
6/27/16
7/8/16
Owner
Tile Hallway and Server Room
14 days over weekends
Tile: 11 days
Grouting/edging: 3 days

7/7/16
7/19/16
Owner
Move items back into vault
7/20/16
7/20/16
Owner
Move items back into server room, reconnections, etc.
7/21/16
7/22/16
Owner
Tiling & Painting Down Time: Music work
S.Order:
  (x)EsQu, ( )Rem, ( )SoFl, ( )Awa, ( )BrDa, ( )ScDr, ( )BlDe, ( )SiDa


(x)EsQu: SQ, PR 

( )Rem: SQ, PR(L-kdb), Vla(var/f...p)

( )SoFl: SQ, PR(up), StdPL?(Pno<->Vib)

( )Awa: SQ, Drms(var/f...p), overall Cmpr?

( )BrDa: SQ, StdPL(Review)

( )ScDr: SQ(!)/F, StdPL, Drms/Improve

( )BlDe: SQ(!)/F, StdPL, PR/Hall, Bass(more+^)

( )SiDa: SQ, StdPL, Hall/PR


 SQ=Sound(Instrument) Quality
 F=Fades
 PR=Presence
 StdPL=Standard Placement (Orchestra)
8/8/16
9/22/16
Owner
Patching cleanup (joint seal, painting, moves, etc.)

9/23/16
10/4/16
Owner
Tile MBR
40 days (approx 220 sf):
4 days of preparation (cleaning, edging, antiF)
26 days of tiling
4 days grouting/edging/electrical/cleanup
10/17 start
Holiday break [55 elapsed]
10/17/16
12/9/16
Owner
Studio
11/13/14
10/24/17
Owner
*Empty out Studio (move to garage or to storage unit)
11/13/14
11/17/14
Owner
Studio drywall Install and primer paint coat
1/28/15
2/4/15
Owner
*Purchase and deliver treatment for studio
2/1/16
2/16/16
Owner
Move items into Studio & Cleanup
5/2/16
5/4/16
Owner
Office Prep, Furniture move, misc.
X Office/LM (5):
  X Finish baseboard work (2)
  X Move desks
  X Add castors to all office furniture
    Very heavy duty (1000 lbs total capacity):
    Everbilt 4" rubber wheeled 250lb (heights are 5"):
      2x rigid(SKU 251 361),2x swivel/lock(SKU 251 263) [5" swivel clear]
      2x leveling 1/2" washers each rigid plate hole (8x): SKU 636 606
    (2x) 4x4 (3.5"x3.5") 23.75" support posts: screwed & glued
    Support angle brackets (4x): TA9Z-R: 8-1/4" length
    16x plate screws (2-1/2" or 3")
    ?x2x2 bracket tapered head nut/bolt to attach to sides of desk
       (countersink head on outside of desk wall)
    ?x2x2 bracket screws (3") (to attach to support post)
    Notes:
      Castors to add only 1/2" in total desk height
        Total desk wall height required: 4.5" castor + 3.5" 4x4 = 8"
      Measure exact height of support posts accordingly
      Drill holes in desk wall and support posts, attach hardware
  X Move furniture
  X Wire up office
     X Add wire molding, X need to have baseboard installed prior
X MBR (2):
  X Add wire track molding and finish putty/paint on connection hole
  X Wire up MBR, test
Bathrooms/Utility (1):
  Finish rest of purchased bathroom hardware (hooks, etc.)
    Center all door hardware even with asymmetric mounts
All rooms (1):
  Install doorstops (use cement screws through the tile into slab)
7/13/17
9/22/17
Owner
Finish upgrade of studio equipment
9/5/17
10/24/17
Owner
Install treatment, wiring and other items for studio
Test wiring
Rack
Rack items
Wiring rack
Wiring to stations
Room treatment
9/25/17
10/3/17
Owner
*Purchase and install finish surfaces: Baseboard,CounterTiles
10/25/17
11/21/17
Owner
Plumbing: finish all interior fixtures to final surfaces, etc.
11/22/17
11/22/17
Owner, Jesse
Power House
11/24/17
1/17/18
Owner
Finalize power house design
Revise to take out roof thermal panel, will use lower temperature (~65-70 degress F) electric water heater run off the PhotoVoltaic panel(s).
*Rework power house design to accomodate the above change*
11/24/17
12/1/17
Owner
Power house RFQ and acceptance
12/4/17
12/12/17
Owner
Construct power house footing, walls and roof
May need to upgrade specific boxes.
12/13/17
1/4/18
Owner
Construct photovoltaic strap footings
12/13/17
12/15/17
Owner
*Purchase and deliver minimum required circuitry for existing panels, no batteries
12/6/17
1/4/18
Owner
Install photovoltaic control circuitry, including inverter
1/5/18
1/9/18
Owner
Install existing photovoltaic arrays
1/10/18
1/11/18
Owner, Dennis
*Purchase and deliver electric heater for ground loop field
12/13/17
1/4/18
Owner
Install electric heater for ground loop field *MILESTONE*
Lower temperature setting (~65-70 degrees F).
Hook up to existing (2) PEX ground loop charging lines.
1/12/18
1/17/18
Owner, Jesse
Computers and Networking
10/15/13
4/6/18
Owner
Thermostat Program - v1 & v2
10/15/13
2/14/14
Owner
Windows XP convert to Linux Xubuntu 14.04
26 years of applications to migrate
Windows/Linux interoperability to configure
Dual boot functionality to maintain, NTFS common disk format
SSO NT4 Domain to establish with roaming/served profiles
Finish java library development for Linux modules (esp. file naming)
3/27/14
12/16/15
Owner
*Purchase and deliver domain/disk server
2/2/15
2/4/15
Owner
Install and configure domain/disk server
2/5/15
4/24/15
Owner
*Purchase and deliver WEL data logger and sensors
1/18/18
1/24/18
Owner
Install WEL data logger and sensors
Run 3-4 home runs to logger.
1/25/18
1/31/18
Owner
Program house controller computer
5W plug computer running Linux.
Applications and control logic developed in Java.
 - Process Control (started)
 - WEL logging
 - Garage exhaust pit monitor/override
 - Thermostat/heat pump monitor/override (80%)
 - Whole house fan monitor/override
 - Exterior window shading monitor/control/override

2/1/18
4/5/18
Owner
Hook up WEL output to house controller computer *MILESTONE*
Hook up in tandem with normal WEL computer website logging.
4/6/18
4/6/18
Owner
Garage
10/24/17
1/24/18
Obtain garage permit
10/24/17
11/20/17
Owner
Plumbing: Prepour and underslab work
11/17/17
11/20/17
Electrical: Prepour and underslab work
Dennis and I - 2 days
11/20/17
11/20/17
Construct garage walls, roof and parapet (EST)
11/21/17
11/30/17
*Purchase and deliver any insulation for garage walls
External dry stack wall: 2" insulation
Module exposed walls both internal and external: on site (plus more?)
11/24/17
11/30/17
Install garage walls insulation
Both external and internal.
12/1/17
12/4/17
Install additional thermal break footing
12/1/17
12/7/17
*Purchase and deliver thermal break insulation for exterior module walls in garage
12/6/17
12/7/17
Install module footing thermal break insulation
Both external and internal.
12/8/17
12/11/17
Construct garage exhaust pit
Needs two more walls and floor.
Install PVC venting pipe: pit and wall.
Install exhaust box in wall and fan, electrical lines back to inside.
Install outside vent cover.
12/12/17
12/12/17
Install garage underslab fill
12/13/17
12/14/17
Garage Slab Pour
Block out garage exhaust pit.
12/15/17
12/21/17
Construct internal garage kennel walls
12/22/17
12/29/17
*Purchase and deliver module walls heat wiring
12/20/17
12/21/17
Install module walls heat wiring
12/22/17
12/26/17
Install module walls thermal break insulation and framed wall
Both external and internal.
12/27/17
12/28/17
Plumbing: Install internal garage plumbing fixtures
12/22/17
12/22/17
Electrical: Install internal garage electrical and lighting
Me - 3 days
12/22/17
12/27/17
Electrical: Install external electrical
All external LED lighting, parapet and patio.
All remaining external building outlets.
Lighted address.
Garage flood lights (front and side).
Me - 5 days
12/28/17
1/4/18
Fabricate garage exhaust control circuit board
10/24/17
10/30/17
Install garage exhaust control circuit and inputs
1/5/18
1/5/18
Purchase and deliver garage vehicle door
12/15/17
12/21/17
Install garage vehicle door
Includes framing.
12/22/17
12/26/17
*Purchase and deliver final set of eight doors
Inside airlock door, BR#2 door, Studio doors (2), Office door, garage doors (3).
11/16/17
12/21/17
Install garage external entry doors (2)
12/22/17
12/22/17
Stucco all external garage walls (final) *MILESTONE*
12/27/17
12/29/17
Plumbing: Install external garage plumbing fixtures
1/2/18
1/2/18
Fill Dirt on top of Garage dome - compact, grade
1/17/18
1/23/18
Garage completed *MILESTONE*
1/24/18
1/24/18
Garage - alternative
10/24/17
12/28/17
Owner
Obtain garage permit
10/24/17
11/20/17
Owner
Purchase and deliver all door header material
10/31/17
11/20/17
Construct garage external walls
Dry Stack block.
Framing for all doors and windows.
Structural tube for vehicle/entry doors.
Headers for front and side doors and windows.
Block out for garage exhaust pit venting.
11/21/17
11/28/17
*Purchase and deliver any insulation for garage walls
External dry stack wall: 2" insulation
Module exposed walls both internal and external: on site (plus more?)
11/21/17
11/28/17
Install garage walls insulation
Both external and internal.
11/29/17
11/30/17
*Purchase and deliver roofing materials
11/14/17
11/28/17
Install garage roof
Roof framing.
Roof top installation.
11/29/17
12/5/17
County inspection: 1610 Roof Construction
12/6/17
12/6/17
Install garage ceiling
12/6/17
12/8/17
Construct internal garage kennel
12/11/17
12/15/17
Plumbing: Install internal garage plumbing fixtures
12/18/17
12/18/17
Electrical: Install internal garage electrical and lighting
Me - 3 days
12/18/17
12/20/17
Owner
Electrical: Install external electrical
All external LED lighting, parapet and patio.
All remaining external building outlets.
Lighted address.
Garage flood lights (front and side).
Me - 5 days
12/21/17
12/28/17
Owner
Fabricate garage exhaust control circuit board
12/14/17
12/20/17
Owner
Install garage exhaust control circuit and inputs
12/21/17
12/21/17
Owner
Purchase and deliver garage vehicle door
11/29/17
12/5/17
Install garage vehicle door
Includes framing.
12/6/17
12/7/17
*Purchase and deliver garage exterior entry doors (2)
11/14/17
12/5/17
Install garage external entry doors (2)
12/6/17
12/6/17
Plumbing: Install external plumbing fixures
All Frost Free faucets at 3 building locations.
The seasonal PEX line run up to the top of the roof.
12/11/17
12/12/17
Garage completed *MILESTONE*
12/29/17
12/29/17
Interior Finishing
7/3/14
1/22/18
Owner
Stain and seal inside windows and front door trim
7/3/14
7/14/14
Owner
Finish interior window framing
12/29/17
1/12/18
Finish interior doors framing
1/16/18
1/22/18
Roof/Parapet Cap
10/24/17
12/8/17
Owner
Stucco all external garage walls *MILESTONE*
12/6/17
12/8/17
Regrade and compact where necessary
10/24/17
10/30/17
Remeld frayed holes in pond liner
10/31/17
10/31/17
Install pond liner cap *MILESTONE*
11/1/17
11/1/17
Install final six doors
Inside airlock door, BR#2 door, Studio doors (2), Office door, garage doors (3).
12/22/17
12/27/17
Owner
Install first set of internal doors - Finish
Trim, hardware
12/28/17
12/29/17
Owner
County inspection: Final Garage / additional interior plumbing
1/25/18
1/25/18
Follow-on tasks - TBD timing
12/1/14
2/9/18
Owner
Purchase and deliver new refrigerator and freezer
12/1/14
12/19/14
Owner
Install new refrigerator and freezer
12/22/14
12/22/14
Owner
Purchase and deliver patio materials and light fixtures
4/1/15
4/7/15
Owner
Install patio and light fixtures
4/8/15
4/10/15
*Purchase and deliver server room and vault cabinets
4/1/15
4/7/15
Owner
Install server room and vault cabinets
4/8/15
4/9/15
*Purchase and deliver driveway gate and fencing
4/1/15
4/9/15
Install driveway gate and fencing
4/10/15
4/13/15
*Purchase and deliver garage cabinets
1/19/18
1/25/18
Install garage cabinets
1/26/18
2/1/18
Move all items to garage/house from studio and storage, close out storage
Utility trailer plus appliance dolly.
2/2/18
2/8/18
*Install garage exhaust pit grate
2/9/18
2/9/18
Install garage/driveway apron
Apron to extend around north kennel are to provide walkway around corner.
Possibly more, needs evaluation.
12/11/17
12/12/17
Purchase and deliver patio materials and light fixtures
12/13/17
12/15/17
Purchase remaining house lighting (tubes, etc.)
7/19/16
8/1/16
Electrical: Install remaining house lighting (tubes, etc.)
Part of this is also constructing the recessed/bounced lighting fixtures,
which requires use of the workshop area in the completed garage.
8/2/16
8/15/16
Owner
*Install front door grate
12/29/17
12/29/17
*Purchase and install fencing for house footprint, dog run
4/1/15
4/7/15
Architectural design of outside service panel enclosure
4/3/15
4/7/15
Construct enclosure for outside service panels
Something quick, easy and low cost.
4/8/15
4/10/15
Construct and install mobile closets
3 closets
1/26/18
2/1/18
Construct and install fold-up beds
Queen size, 2 beds.
Need to purchase special hardware separately.
Models in stores are way to expensive for what the product is.
2/2/18
2/8/18
*Purchase and deliver exterior window quilted rollup shades (inside)
4/1/15
4/21/15
Install exterior window quilted rollup shades (inside)
4/1/15
4/9/15
*Purchase and deliver items for media center
4/15/15
4/21/15
Install items for media center
Furniture, shelving, media devices.  Ability to hook up to computers.
4/22/15
4/23/15
Construct or purchase floor lamps for media center
Probably purchase, regular LED bulb compatable
4/24/15
4/27/15
Owner
*Purchase and deliver planterbed materials
4/21/15
4/27/15
Construct and install planterbeds
Note: use left over PVC tubes: (a) seal bottoms of planterbed boxes, (b) cut PVC to proper lengths, (c) drill weep holes in sides, (d) install in dry well gravel beds.
4/28/15
5/11/15
*Purchase and install exterior windows sunshade
Will not need until at least summer of 2014.
Will need to fine tune type, materials, attaching, etc.
12/11/17
12/22/17
*Purchase and deliver all remaining photovoltaic equipment
1/10/18
1/17/18