Construction - Completion Phase
|
Name |
Begin date |
End date |
Resources |
Apply/Get loan
|
8/1/13
|
10/23/17
| Owner |
Get Garage bid and official draft design documents
Finalize garage design details with Carlos Get bid from Jeff Get submittal quality design files from Jeff EST or local general to have Oregon Contractor's license |
6/30/14
|
10/30/17
| Owner |
Get concrete plaster finish bid
Get bid from Marc |
6/3/14
|
7/28/14
| Owner |
Stain and finish cabinets and doors
|
8/9/13
|
8/30/13
| Owner |
Purchase and install cabinet hardware
|
8/28/13
|
8/29/13
| Owner |
Purchase and install water heater blanket and timer
|
8/21/13
|
9/6/13
| Owner |
Purchase and install kitchen undercabinet LED task lighting
|
12/4/13
|
8/22/14
| Owner |
Finish concrete walls and floors 80%
|
1/20/16
|
9/22/17
| Owner, Hitson |
Plaster 80% interior bare concrete
|
1/20/16
|
3/2/16
| Hitson |
Plaster Studio
|
1/20/16
|
1/28/16
| Hitson |
Plaster BR2
|
2/2/16
|
2/3/16
| Hitson |
Plaster Office
|
2/4/16
|
2/5/16
| Hitson |
Plaster BM half dome
|
2/8/16
|
2/9/16
| Hitson |
Plaster Kitchen
|
2/12/16
|
2/12/16
| Hitson |
Plaster LM 3/4 dome
|
2/16/16
|
2/19/16
| Hitson |
Plaster remaining 80%
|
2/24/16
|
3/2/16
| Hitson |
Paint 80% interior plaster
|
2/5/16
|
8/5/16
| Owner |
Paint Studio
5 days, over weekend |
2/5/16
|
2/9/16
| Owner |
Paint BM Half Dome
|
4/25/16
|
5/3/16
| Owner |
Paint BR2 & South overhang/walls
4 days over weekend (and move items out) |
5/4/16
|
5/10/16
| Owner |
Paint Kitchen & Front Door airlock
3 days over weekend |
7/19/16
|
7/19/16
| Owner |
Paint LM Full Dome and walls
12 days over weekend |
7/26/16
|
8/5/16
| Owner |
Floor Tile 80%
|
2/1/16
|
9/22/17
| Owner |
*Purchase and deliver Studio and Office Tile Materials
|
2/1/16
|
2/4/16
| Owner |
Tile Studio
|
2/10/16
|
4/29/16
| Owner |
*Purchase and deliver Tile materials for remaining LM areas
|
12/5/16
|
12/7/16
| Owner |
Tile BR2 with hallway entrance
23 days (approx 162 sf BR2, 24 sf hallway entrance) 3 days preparation (cleaning, edging, antiF, baselining) 18 days tiling 4 days grouting/edging 1 week Holiday break Elapsed days: 42 |
12/12/16
|
1/20/17
| Owner |
Tile north LM partial
57 days (approx 408 sf / 203 pcs) (52+36+36+34/36+22/26+17) 10 days preparation (clearing, cleaning, edging, antiF, baselining) 35 days tiling 12 days grouting/edging |
1/23/17
|
5/26/17
| Owner |
Tile Office
17 days (approx 112 sf, 54 pieces) 4 days preparation (clearing, vents, cleaning, edging, antiF, baselining) 9 days tiling 4 days grouting/edging |
4/10/17
|
5/2/17
| Owner |
Tile Kitchen
14 days (approx 70 sf) 2 days preparation (clearing, cleaning, edging, antiF, baselining) 7 days tiling 5 days grouting/edging/re-setup |
5/3/17
|
5/19/17
| Owner |
Tile south LM partial
38 days (approx 266 sf) 7 days preparation (clearing, vents/outlet, 2xsensorsruns, cleaning, edging, antiF, baselining) 23 days tiling 7/8 days grouting/edging |
5/23/17
|
7/13/17
| Owner |
Tiling Finish Tasks
X MBR (1): X Touch up base paint X Office/LM (2): X Finish covering/grouting 3 vents Bathrooms/Utility (3): Finish grout edging Finish tub grout Finish Heat Pump sleaves and caps LM Media Center/Dining (1): Install electrical floor outlets |
7/13/17
|
9/22/17
| Owner |
Plaster, Painting, Tiling completed *MILESTONE*
|
9/25/17
|
9/25/17
| Owner |
Stucco all external house walls (base) *MILESTONE*
|
10/10/13
|
11/18/13
| Owner |
Laying/block down slab exterior 8" interim insulation
|
11/19/13
|
11/19/13
| Owner |
Finish concrete walls and floors 20%
|
5/9/16
|
12/9/16
| Owner, Hitson |
Prep utility, server, vault, 1/2 bath, MBR
5 days over weekend 1/2 bath Clean expansion joint Remove server room and vault contents Cut outlet power Remove server case from wall Loosen all power and data conduits and boxes from wall Clean expansion joints MBR Move bedroom items to BR2 Clean expansion joints Wash all laundry Utility room Remove contents Move washer/dryer Loosen all power conduits and piping from wall (accessable only) Clean expansion joints (accessable only) |
5/9/16
|
5/13/16
| Owner |
Plumbing prep: Utility and Half Bath
Pull Half Bath toilet, hot water heater and heat pump tank |
5/13/16
|
5/13/16
| Jesse |
Plaster 20% interior bare concrete Utility, Half-Bath first
Utility room Half Bath Vault (entirely cover door, hinges, flange) Server room MBR |
5/13/16
|
6/1/16
| Hitson |
Plaster Utility and Half Bath
Utility room Half Bath Vault (entirely cover door, hinges, flange) Server room MBR |
5/13/16
|
5/16/16
| Hitson |
Plaster Vault and Server Room
Utility room Half Bath Vault (entirely cover door, hinges, flange) Server room MBR |
5/17/16
|
5/19/16
| Hitson |
Plaster MBR
Utility room Half Bath Vault (entirely cover door, hinges, flange) Server room MBR |
5/27/16
|
6/1/16
| Hitson |
Finish Patch Areas Utility and Half Bath
|
5/17/16
|
5/27/16
| Owner |
Floor Prep: Utility and Half Bath
Day 1: Strip sealer Day 2: Edging and Anti-fracture membrane. Rough tile layout. Day 3: Thin-set leveling. Layout exact tile placement. |
5/17/16
|
5/19/16
| Owner |
Floor Tile patch: Utility and Half Bath
3 days over weekend |
5/20/16
|
5/23/16
| Owner |
Floor Grout/edging patch: Utility and Half Bath
Grout near Utility room edge first Install patch edging right after grouting drys enough to remove edging wood |
5/24/16
|
5/25/16
| Owner |
Paint 20% Utility and Half Bath
All three coats in one day, forced drying with fan 8am-10am, 12pm-2pm, 4pm-6pm |
5/25/16
|
5/25/16
| Owner |
Floor cleanup patch: Utility and Half Bath
Wash, remove any grit, etc. Remove all tape from lines, etc., reattach to wall, cleanup. |
5/27/16
|
5/27/16
| Owner |
Plumbing work
Reinstall Half Bath toilet, hot water heater and heat pump tank Pull Full Bath toilet |
5/27/16
|
5/27/16
| Jesse |
*Purchase and deliver Tile materials for MBR, hall, baths, utility, server and vault
|
5/16/16
|
5/17/16
| Owner |
Floor Tile: Utility and baths remaining areas
Remaining Utility area. All of the Full Bathroom 11 days over weekend |
5/31/16
|
6/8/16
| Owner |
Plumbing finish
Reinstall Full Bath Toilet |
6/7/16
|
6/7/16
| Jesse |
Start: Paint 20% Remaining
Vault, Server Room, MBR 1 day start |
6/8/16
|
6/8/16
| Owner |
Downtime
|
6/9/16
|
6/15/16
| Owner |
Finish: Paint 20% Remaining
Vault, Server Room, MBR 7 days over weekend |
6/16/16
|
6/24/16
| Owner |
Floor Tile 20%
Water Heater patching (wall,floor) Day 1: Pull water heater, strip cement patch, sealer, self-leveler Day 2: 8-9am: wall primer, 11-12pm: wall primer, 2-3pm: finish coat 4-5pm: Tile Day 3: Reinstall water heater Priority: Utility-A,1/2 bath, Bath-A Marc/Jesse Utility-B, Bath-B Jesse MBR, Hallway Vault, ServerRoom |
6/27/16
|
12/9/16
| Owner |
Tile Vault
9 days over weekend: 3 days prep (all): Clean, edging, antiF Vault level 4 days tiling 1 day grouting 1 day edging, cleanup |
6/27/16
|
7/8/16
| Owner |
Tile Hallway and Server Room
14 days over weekends Tile: 11 days Grouting/edging: 3 days |
7/7/16
|
7/19/16
| Owner |
Move items back into vault
|
7/20/16
|
7/20/16
| Owner |
Move items back into server room, reconnections, etc.
|
7/21/16
|
7/22/16
| Owner |
Tiling & Painting Down Time: Music work
S.Order: (x)EsQu, ( )Rem, ( )SoFl, ( )Awa, ( )BrDa, ( )ScDr, ( )BlDe, ( )SiDa (x)EsQu: SQ, PR ( )Rem: SQ, PR(L-kdb), Vla(var/f...p) ( )SoFl: SQ, PR(up), StdPL?(Pno<->Vib) ( )Awa: SQ, Drms(var/f...p), overall Cmpr? ( )BrDa: SQ, StdPL(Review) ( )ScDr: SQ(!)/F, StdPL, Drms/Improve ( )BlDe: SQ(!)/F, StdPL, PR/Hall, Bass(more+^) ( )SiDa: SQ, StdPL, Hall/PR SQ=Sound(Instrument) Quality F=Fades PR=Presence StdPL=Standard Placement (Orchestra) |
8/8/16
|
9/22/16
| Owner |
Patching cleanup (joint seal, painting, moves, etc.)
|
9/23/16
|
10/4/16
| Owner |
Tile MBR
40 days (approx 220 sf): 4 days of preparation (cleaning, edging, antiF) 26 days of tiling 4 days grouting/edging/electrical/cleanup 10/17 start Holiday break [55 elapsed] |
10/17/16
|
12/9/16
| Owner |
Studio
|
11/13/14
|
10/24/17
| Owner |
*Empty out Studio (move to garage or to storage unit)
|
11/13/14
|
11/17/14
| Owner |
Studio drywall Install and primer paint coat
|
1/28/15
|
2/4/15
| Owner |
*Purchase and deliver treatment for studio
|
2/1/16
|
2/16/16
| Owner |
Move items into Studio & Cleanup
|
5/2/16
|
5/4/16
| Owner |
Office Prep, Furniture move, misc.
X Office/LM (5): X Finish baseboard work (2) X Move desks X Add castors to all office furniture Very heavy duty (1000 lbs total capacity): Everbilt 4" rubber wheeled 250lb (heights are 5"): 2x rigid(SKU 251 361),2x swivel/lock(SKU 251 263) [5" swivel clear] 2x leveling 1/2" washers each rigid plate hole (8x): SKU 636 606 (2x) 4x4 (3.5"x3.5") 23.75" support posts: screwed & glued Support angle brackets (4x): TA9Z-R: 8-1/4" length 16x plate screws (2-1/2" or 3") ?x2x2 bracket tapered head nut/bolt to attach to sides of desk (countersink head on outside of desk wall) ?x2x2 bracket screws (3") (to attach to support post) Notes: Castors to add only 1/2" in total desk height Total desk wall height required: 4.5" castor + 3.5" 4x4 = 8" Measure exact height of support posts accordingly Drill holes in desk wall and support posts, attach hardware X Move furniture X Wire up office X Add wire molding, X need to have baseboard installed prior X MBR (2): X Add wire track molding and finish putty/paint on connection hole X Wire up MBR, test Bathrooms/Utility (1): Finish rest of purchased bathroom hardware (hooks, etc.) Center all door hardware even with asymmetric mounts All rooms (1): Install doorstops (use cement screws through the tile into slab) |
7/13/17
|
9/22/17
| Owner |
Finish upgrade of studio equipment
|
9/5/17
|
10/24/17
| Owner |
Install treatment, wiring and other items for studio
Test wiring Rack Rack items Wiring rack Wiring to stations Room treatment |
9/25/17
|
10/3/17
| Owner |
*Purchase and install finish surfaces: Baseboard,CounterTiles
|
10/25/17
|
11/21/17
| Owner |
Plumbing: finish all interior fixtures to final surfaces, etc.
|
11/22/17
|
11/22/17
| Owner, Jesse |
Power House
|
11/24/17
|
1/17/18
| Owner |
Finalize power house design
Revise to take out roof thermal panel, will use lower temperature (~65-70 degress F) electric water heater run off the PhotoVoltaic panel(s). *Rework power house design to accomodate the above change* |
11/24/17
|
12/1/17
| Owner |
Power house RFQ and acceptance
|
12/4/17
|
12/12/17
| Owner |
Construct power house footing, walls and roof
May need to upgrade specific boxes. |
12/13/17
|
1/4/18
| Owner |
Construct photovoltaic strap footings
|
12/13/17
|
12/15/17
| Owner |
*Purchase and deliver minimum required circuitry for existing panels, no batteries
|
12/6/17
|
1/4/18
| Owner |
Install photovoltaic control circuitry, including inverter
|
1/5/18
|
1/9/18
| Owner |
Install existing photovoltaic arrays
|
1/10/18
|
1/11/18
| Owner, Dennis |
*Purchase and deliver electric heater for ground loop field
|
12/13/17
|
1/4/18
| Owner |
Install electric heater for ground loop field *MILESTONE*
Lower temperature setting (~65-70 degrees F). Hook up to existing (2) PEX ground loop charging lines. |
1/12/18
|
1/17/18
| Owner, Jesse |
Computers and Networking
|
10/15/13
|
4/6/18
| Owner |
Thermostat Program - v1 & v2
|
10/15/13
|
2/14/14
| Owner |
Windows XP convert to Linux Xubuntu 14.04
26 years of applications to migrate Windows/Linux interoperability to configure Dual boot functionality to maintain, NTFS common disk format SSO NT4 Domain to establish with roaming/served profiles Finish java library development for Linux modules (esp. file naming) |
3/27/14
|
12/16/15
| Owner |
*Purchase and deliver domain/disk server
|
2/2/15
|
2/4/15
| Owner |
Install and configure domain/disk server
|
2/5/15
|
4/24/15
| Owner |
*Purchase and deliver WEL data logger and sensors
|
1/18/18
|
1/24/18
| Owner |
Install WEL data logger and sensors
Run 3-4 home runs to logger. |
1/25/18
|
1/31/18
| Owner |
Program house controller computer
5W plug computer running Linux. Applications and control logic developed in Java. - Process Control (started) - WEL logging - Garage exhaust pit monitor/override - Thermostat/heat pump monitor/override (80%) - Whole house fan monitor/override - Exterior window shading monitor/control/override |
2/1/18
|
4/5/18
| Owner |
Hook up WEL output to house controller computer *MILESTONE*
Hook up in tandem with normal WEL computer website logging. |
4/6/18
|
4/6/18
| Owner |
Garage
|
10/24/17
|
1/24/18
| |
Obtain garage permit
|
10/24/17
|
11/20/17
| Owner |
Plumbing: Prepour and underslab work
|
11/17/17
|
11/20/17
| |
Electrical: Prepour and underslab work
Dennis and I - 2 days |
11/20/17
|
11/20/17
| |
Construct garage walls, roof and parapet (EST)
|
11/21/17
|
11/30/17
| |
*Purchase and deliver any insulation for garage walls
External dry stack wall: 2" insulation Module exposed walls both internal and external: on site (plus more?) |
11/24/17
|
11/30/17
| |
Install garage walls insulation
Both external and internal. |
12/1/17
|
12/4/17
| |
Install additional thermal break footing
|
12/1/17
|
12/7/17
| |
*Purchase and deliver thermal break insulation for exterior module walls in garage
|
12/6/17
|
12/7/17
| |
Install module footing thermal break insulation
Both external and internal. |
12/8/17
|
12/11/17
| |
Construct garage exhaust pit
Needs two more walls and floor. Install PVC venting pipe: pit and wall. Install exhaust box in wall and fan, electrical lines back to inside. Install outside vent cover. |
12/12/17
|
12/12/17
| |
Install garage underslab fill
|
12/13/17
|
12/14/17
| |
Garage Slab Pour
Block out garage exhaust pit. |
12/15/17
|
12/21/17
| |
Construct internal garage kennel walls
|
12/22/17
|
12/29/17
| |
*Purchase and deliver module walls heat wiring
|
12/20/17
|
12/21/17
| |
Install module walls heat wiring
|
12/22/17
|
12/26/17
| |
Install module walls thermal break insulation and framed wall
Both external and internal. |
12/27/17
|
12/28/17
| |
Plumbing: Install internal garage plumbing fixtures
|
12/22/17
|
12/22/17
| |
Electrical: Install internal garage electrical and lighting
Me - 3 days |
12/22/17
|
12/27/17
| |
Electrical: Install external electrical
All external LED lighting, parapet and patio. All remaining external building outlets. Lighted address. Garage flood lights (front and side). Me - 5 days |
12/28/17
|
1/4/18
| |
Fabricate garage exhaust control circuit board
|
10/24/17
|
10/30/17
| |
Install garage exhaust control circuit and inputs
|
1/5/18
|
1/5/18
| |
Purchase and deliver garage vehicle door
|
12/15/17
|
12/21/17
| |
Install garage vehicle door
Includes framing. |
12/22/17
|
12/26/17
| |
*Purchase and deliver final set of eight doors
Inside airlock door, BR#2 door, Studio doors (2), Office door, garage doors (3). |
11/16/17
|
12/21/17
| |
Install garage external entry doors (2)
|
12/22/17
|
12/22/17
| |
Stucco all external garage walls (final) *MILESTONE*
|
12/27/17
|
12/29/17
| |
Plumbing: Install external garage plumbing fixtures
|
1/2/18
|
1/2/18
| |
Fill Dirt on top of Garage dome - compact, grade
|
1/17/18
|
1/23/18
| |
Garage completed *MILESTONE*
|
1/24/18
|
1/24/18
| |
Garage - alternative
|
10/24/17
|
12/28/17
| Owner |
Obtain garage permit
|
10/24/17
|
11/20/17
| Owner |
Purchase and deliver all door header material
|
10/31/17
|
11/20/17
| |
Construct garage external walls
Dry Stack block. Framing for all doors and windows. Structural tube for vehicle/entry doors. Headers for front and side doors and windows. Block out for garage exhaust pit venting. |
11/21/17
|
11/28/17
| |
*Purchase and deliver any insulation for garage walls
External dry stack wall: 2" insulation Module exposed walls both internal and external: on site (plus more?) |
11/21/17
|
11/28/17
| |
Install garage walls insulation
Both external and internal. |
11/29/17
|
11/30/17
| |
*Purchase and deliver roofing materials
|
11/14/17
|
11/28/17
| |
Install garage roof
Roof framing. Roof top installation. |
11/29/17
|
12/5/17
| |
County inspection: 1610 Roof Construction
|
12/6/17
|
12/6/17
| |
Install garage ceiling
|
12/6/17
|
12/8/17
| |
Construct internal garage kennel
|
12/11/17
|
12/15/17
| |
Plumbing: Install internal garage plumbing fixtures
|
12/18/17
|
12/18/17
| |
Electrical: Install internal garage electrical and lighting
Me - 3 days |
12/18/17
|
12/20/17
| Owner |
Electrical: Install external electrical
All external LED lighting, parapet and patio. All remaining external building outlets. Lighted address. Garage flood lights (front and side). Me - 5 days |
12/21/17
|
12/28/17
| Owner |
Fabricate garage exhaust control circuit board
|
12/14/17
|
12/20/17
| Owner |
Install garage exhaust control circuit and inputs
|
12/21/17
|
12/21/17
| Owner |
Purchase and deliver garage vehicle door
|
11/29/17
|
12/5/17
| |
Install garage vehicle door
Includes framing. |
12/6/17
|
12/7/17
| |
*Purchase and deliver garage exterior entry doors (2)
|
11/14/17
|
12/5/17
| |
Install garage external entry doors (2)
|
12/6/17
|
12/6/17
| |
Plumbing: Install external plumbing fixures
All Frost Free faucets at 3 building locations. The seasonal PEX line run up to the top of the roof. |
12/11/17
|
12/12/17
| |
Garage completed *MILESTONE*
|
12/29/17
|
12/29/17
| |
Interior Finishing
|
7/3/14
|
1/22/18
| Owner |
Stain and seal inside windows and front door trim
|
7/3/14
|
7/14/14
| Owner |
Finish interior window framing
|
12/29/17
|
1/12/18
| |
Finish interior doors framing
|
1/16/18
|
1/22/18
| |
Roof/Parapet Cap
|
10/24/17
|
12/8/17
| Owner |
Stucco all external garage walls *MILESTONE*
|
12/6/17
|
12/8/17
| |
Regrade and compact where necessary
|
10/24/17
|
10/30/17
| |
Remeld frayed holes in pond liner
|
10/31/17
|
10/31/17
| |
Install pond liner cap *MILESTONE*
|
11/1/17
|
11/1/17
| |
Install final six doors
Inside airlock door, BR#2 door, Studio doors (2), Office door, garage doors (3). |
12/22/17
|
12/27/17
| Owner |
Install first set of internal doors - Finish
Trim, hardware |
12/28/17
|
12/29/17
| Owner |
County inspection: Final Garage / additional interior plumbing
|
1/25/18
|
1/25/18
| |
Follow-on tasks - TBD timing
|
12/1/14
|
2/9/18
| Owner |
Purchase and deliver new refrigerator and freezer
|
12/1/14
|
12/19/14
| Owner |
Install new refrigerator and freezer
|
12/22/14
|
12/22/14
| Owner |
Purchase and deliver patio materials and light fixtures
|
4/1/15
|
4/7/15
| Owner |
Install patio and light fixtures
|
4/8/15
|
4/10/15
| |
*Purchase and deliver server room and vault cabinets
|
4/1/15
|
4/7/15
| Owner |
Install server room and vault cabinets
|
4/8/15
|
4/9/15
| |
*Purchase and deliver driveway gate and fencing
|
4/1/15
|
4/9/15
| |
Install driveway gate and fencing
|
4/10/15
|
4/13/15
| |
*Purchase and deliver garage cabinets
|
1/19/18
|
1/25/18
| |
Install garage cabinets
|
1/26/18
|
2/1/18
| |
Move all items to garage/house from studio and storage, close out storage
Utility trailer plus appliance dolly. |
2/2/18
|
2/8/18
| |
*Install garage exhaust pit grate
|
2/9/18
|
2/9/18
| |
Install garage/driveway apron
Apron to extend around north kennel are to provide walkway around corner. Possibly more, needs evaluation. |
12/11/17
|
12/12/17
| |
Purchase and deliver patio materials and light fixtures
|
12/13/17
|
12/15/17
| |
Purchase remaining house lighting (tubes, etc.)
|
7/19/16
|
8/1/16
| |
Electrical: Install remaining house lighting (tubes, etc.)
Part of this is also constructing the recessed/bounced lighting fixtures, which requires use of the workshop area in the completed garage. |
8/2/16
|
8/15/16
| Owner |
*Install front door grate
|
12/29/17
|
12/29/17
| |
*Purchase and install fencing for house footprint, dog run
|
4/1/15
|
4/7/15
| |
Architectural design of outside service panel enclosure
|
4/3/15
|
4/7/15
| |
Construct enclosure for outside service panels
Something quick, easy and low cost. |
4/8/15
|
4/10/15
| |
Construct and install mobile closets
3 closets |
1/26/18
|
2/1/18
| |
Construct and install fold-up beds
Queen size, 2 beds. Need to purchase special hardware separately. Models in stores are way to expensive for what the product is. |
2/2/18
|
2/8/18
| |
*Purchase and deliver exterior window quilted rollup shades (inside)
|
4/1/15
|
4/21/15
| |
Install exterior window quilted rollup shades (inside)
|
4/1/15
|
4/9/15
| |
*Purchase and deliver items for media center
|
4/15/15
|
4/21/15
| |
Install items for media center
Furniture, shelving, media devices. Ability to hook up to computers. |
4/22/15
|
4/23/15
| |
Construct or purchase floor lamps for media center
Probably purchase, regular LED bulb compatable |
4/24/15
|
4/27/15
| Owner |
*Purchase and deliver planterbed materials
|
4/21/15
|
4/27/15
| |
Construct and install planterbeds
Note: use left over PVC tubes: (a) seal bottoms of planterbed boxes, (b) cut PVC to proper lengths, (c) drill weep holes in sides, (d) install in dry well gravel beds. |
4/28/15
|
5/11/15
| |
*Purchase and install exterior windows sunshade
Will not need until at least summer of 2014. Will need to fine tune type, materials, attaching, etc. |
12/11/17
|
12/22/17
| |
*Purchase and deliver all remaining photovoltaic equipment
|
1/10/18
|
1/17/18
|
Ganttproject (2.6.6 Brno (build 1715)) | ganttproject.biz
9/17/17 - 6:13:20 PM |